What should you do before you start?
Work through five steps in order, and do not let any trade start until the last one is done.
- Step 1: Check your build date. If it's before 1990, asbestos testing is required before any renovation or demolition work.
- Step 2: Book an asbestos audit. A qualified assessor inspects the areas being renovated and collects samples for lab testing ($400–$1,200).
- Step 3: Wait for the lab report. Don't start any work until you have the written results (2–5 business days).
- Step 4: If asbestos is found — get removal quotes. All asbestos must be removed from the renovation area before building work starts.
- Step 5: Removal, clearance and then renovation. Once the removalist provides a clearance certificate, your builder can start.
Where is asbestos found in renovation areas?
Asbestos turns up most often in wet areas, eaves and floor coverings.
- Bathroom and laundry walls (wet-area sheeting)
- Kitchen splashbacks behind old tiles
- Eaves when extending or adding a verandah
- Internal walls when opening up floor plans
- Floor vinyl and adhesive when replacing flooring
- Roof when re-roofing or adding skylights
What does the law require before a renovation in SA?
The work health and safety rules apply from the moment a builder or tradesperson starts. A home becomes a workplace when demolition or refurbishment begins.
- A competent person must inspect for asbestos that the work is likely to disturb. Homes do not need a formal asbestos register.
- Samples must be analysed by a NATA-accredited laboratory.
- Where the inspector is unsure, or an area cannot be reached, asbestos must be assumed to be present.
- Asbestos likely to be disturbed must be removed before the work starts, so far as is reasonably practicable.
- The owner and occupier must be told when asbestos is found or assumed.
How much time and money should you allow?
Allow two to three weeks and a few thousand dollars for a typical room. Ask each removalist whether air monitoring, clearance and disposal are inside their price.
| Step | Typical time | Typical Adelaide cost |
|---|---|---|
| Asbestos audit and lab results | About 1 week | $400–$1,200 |
| SafeWork SA notification | 5 days before removal | Included in removal quotes |
| Bathroom or wet-area removal | 1–2 days | $1,500–$4,500 |
| Eaves and soffits, whole house | 1–3 days | $2,000–$6,500 |
| Air monitoring and clearance | At the end of removal | $400–$2,000 |
What happens if you don't test?
Aside from the legal requirement, disturbing asbestos without proper containment releases fibres into the air — a serious health hazard for everyone on site, your family and neighbours.
Penalties for unlicensed removal reach $20,000. Your builder should refuse to start work on a pre-1990 property without an asbestos clearance.
Asbestos found halfway through a job stops work in that area until it is tested and removed, and the notification period then runs while your trades wait.
Common questions
Does my builder arrange asbestos testing?
Some do, but it's your responsibility as the property owner. Getting your own audit before you brief the builder is often faster and cheaper.
How long does the whole process take?
Testing: 1 week (inspection + lab results). Removal (if needed): 1–5 days depending on scope, plus the 5-day SafeWork SA notification. Budget 2–3 weeks before renovation can start.
Do I need to check for asbestos before drilling or small repairs?
Yes. National guidance is to check before any repair, maintenance or renovation, even minor drilling. Either have the material tested or assume it contains asbestos. Never use power tools, sanding or high-pressure water on asbestos cement.
Can I do the demolition myself to save money?
Owners are not legally required to hold a licence to remove non-friable asbestos from their own home, but the SA Government recommends licensed removal, and friable asbestos must be removed by a licensed removalist. Once your builder is on site the licence limits apply to them.
Sources
- Asbestos SA (SA Government): Demolition and refurbishment
- Asbestos SA (SA Government): Homeowners
- SafeWork SA: Notification of asbestos removal
- Asbestos and Silica Safety and Eradication Agency: Householders and home renovators
- What's the Damage: Asbestos removal cost in Adelaide
Last reviewed .